TSMC Commences Phase 3 Construction Of GigaFab

Jan. 17, 2012
TSMC held a groundbreaking ceremony in Taichung’s Central Taiwan Science Park for Phase 3 of its Fab 15 GigaFab.

Taichung, Taiwan: TSMC held a groundbreaking ceremony in Taichung’s Central Taiwan Science Park for Phase 3 of its Fab 15 GigaFab. Phase 3, which will involve 20nm and more advanced process nodes, plans to maintain a capacity of 40,000 300mm wafers per month.

TSMC began Phase 1 construction of Fab 15 in July 2010, and completed equipment move-in in mid-2011 (volume production is slated for early 2012). Phase 2 of Fab 15, which started construction in mid-2011, is expected to begin volume production next year.

Phases 1 and 2 are forecast to generate as much as $3 billion (U.S.) in revenue per year once they enter volume production. TSMC expects Phase 3 to reach a similar scale in the future. Fab 15 currently employs about 1400 employees, and anticipates the creation of 8000 job opportunities.

Phase 3 will represent TSMC’s second GigaFab equipped for 20nm process technology, and the company’s third “green fab” following Fab 12 and Fab 14. Phase 3 applies numerous pollution prevention and energy conservation methods, including classification of process wastewater into 25 categories, a process water-recycling rate of 90%, water-use reduction of 62%, and 5% less power consumption than earlier facilities.

In addition, Phase 3 will feature a rainwater collection surface of 40,000 square meters. All collected rainwater is used in landscaping, consuming no water from public utilities.

About the Author

Staff

Articles, galleries, and recent work by members of Electronic Design's editorial staff.

Sponsored Recommendations

Comments

To join the conversation, and become an exclusive member of Electronic Design, create an account today!